Karachi Building Collapse Death Toll Rises to 11 as Rescuers Recover Three More Bodies

Karachi building collapse death toll reaches 11 as rescuers recover three more bodies. Authorities investigate illegal construction and negligence.

Stay Connected, Stay Informed - Follow News Alert on WhatsApp for Real-time Updates!

The death toll from the collapse of an under-construction building in Karachi has risen to 11 after rescue teams recovered three more bodies from beneath the rubble on Saturday, November 28.

The six-storey building collapsed on November 25 in Karachi Administration Cooperative Housing Society (KAECHS), leaving several construction workers trapped under the debris.

Rescue officials said search and recovery operations were continuing, with teams using heavy machinery and specialised equipment to locate people who might still be buried beneath the remains of the structure.

Around 30 labourers were reportedly present inside the building when it collapsed.

Rescue Operation Continues as Workers Remain Missing

The recovery of three additional bodies brought the confirmed death toll to 11.

Rescue teams have been working continuously to clear the debris and reach areas where construction workers were believed to be trapped.

On Friday, emergency personnel rescued a 28-year-old construction worker, Muhammad Adil, who had survived approximately 54 hours beneath the rubble.

Rescue 1122 officials described his recovery as a major breakthrough. The survivor reportedly informed rescuers that two other people might also be alive in the same area, prompting additional search efforts.

However, rescuers were unable to locate the individuals he had mentioned.

According to information collected from relatives at the rescue operation’s information desk, at least eight people were still missing following Saturday’s recovery operation.

Building Allegedly Constructed Beyond Approved Plan

Initial findings have raised serious questions about violations of construction regulations.

According to information presented during the investigation, permission had been granted for a building consisting of a basement, ground floor and one additional storey. However, six additional floors were allegedly constructed beyond the approved plan.

Police have been investigating whether violations of building regulations, the use of substandard construction materials and possible negligence contributed to the collapse.

The incident has also prompted authorities to examine the role of building owners, contractors, architects, structural engineers and relevant regulatory officials.

Karachi Building Collapse: CM Murad Orders Removal of SBCA Chief, Suspension of 16 Officers

Government Takes Action Against Officials

Sindh Chief Minister Murad Ali Shah ordered action against several officials following the tragedy.

The chief minister directed the removal of senior Sindh Building Control Authority (SBCA) official Waseem Shamshad, who was also serving as the local government secretary.

He also ordered the removal of East Deputy Commissioner Nasrullah Abbasi and SSP East Zubair Sheikh over alleged negligence.

In addition, 16 SBCA officials were ordered to be suspended, while the police were directed to arrest the building’s owner, Salman Tahir, and builder Zeeshan.

Authorities also sealed other under-construction buildings in the area as part of a wider crackdown on unauthorised construction.

Four Suspects Sent on Five-Day Police Remand

A judicial magistrate in Karachi granted police five-day physical remand of four suspects arrested in connection with the building collapse.

The suspects were produced before the court as investigators sought additional time to establish their roles in the incident.

During the hearing, the investigating officer told the court that construction permission had been granted for a much smaller building, but six additional storeys had allegedly been constructed.

The defence questioned the arrests, arguing that some of the detained individuals were workers or relatives of those involved in construction rather than the actual owners or contractors.

The court also questioned why the building owner, contractor and relevant SBCA officials had not all been brought before the investigation process.

It directed the investigating officer to submit a progress report at the next hearing.

Investigation Into Karachi Building Safety Continues

The tragedy has renewed concerns about unauthorised construction and enforcement of building regulations in Karachi.

According to a report submitted by the Karachi Commissioner’s Office, 516 buildings had been sealed across the city as part of an ongoing operation against illegal and unauthorised structures as of November 27.

Authorities have also collected construction material samples from the collapsed building to determine whether the structure met the required safety standards.

Rescue operations and investigations are continuing as families await information about missing workers and authorities seek to establish responsibility for the deadly collapse.

Editorial Source Note: Based on reporting by The Express Tribune, November 28, 2026, with additional details cross-checked against Dawn. The allegations concerning unauthorised construction and negligence remain subject to investigation and legal proceedings.

Leave a Comment

This material may not be published, broadcast, rewritten, redistributed or derived from.
Unless otherwise stated, all content is copyrighted © 2026 News Alert.